Tube Bundle Change-Out
Refinery - Coffeyville, Ks

Remove the tube bundle of 120 psig steam generator.  This was a “Red Line” (high priority) job, which was completed during an unplanned turnaround at the refinery.  Taylor crews worked 24 hours a day for seven (7) days until the work was completed.  Safety was a major factor, and the project was completed on time, with no safety incidents and to the client’s satisfaction.

  • Installation of (2) towers was required to support Taylor’s beam and skating tools, which were necessary
    to remove tube bundle 80 feet “off grade”
  • Utilize 140 ton truck crane to lift and lower the 72K lb. tube bundle
Transported the tube bundle to a repair facility in Houston, TX